Sunday, July 15, 2012

ED CONVEYOR FABRICATION STATUS: 15 JULY 2012

 1. Spray booth: Booth / Spray Pipe / Spray nozzle & accessories
 2. ED cirulation filtration & Accessories
 3. ED Spray booth / chiller / Cooling tower / ED room & structure
 4. Top spray booth / spray booth structure & circulation piping
 5. Oven partition for pre heat & conveyor tension adjusble unit
6. Rectifier / ED pump & order accessories
7. UF & Heat exchanger circulaion pump (Stainless steel)

15-JULY-2012 NEWS UPDATE
Refer to Taiwan fabrication status about 80% completion, we still continue to improve our progress, current we still waiting for the USA standard part's purchase and our target shipment dated on: 24/JULY/2012... for local fabrication with started in bukit beruntung ist week of AUG/2012

Status & Remark:
1. Taiwan  Shipment dated on 24/JULY/2012
2. Master schedule new revision: Rev 04 (Revise: More detail for installation and man power  
    arrangement)
   (Estimate schedule)
   - ETD Taiwan Port: 24/JULY/2012
   - ETA Port Klang  : 08/AUG/2012
   - ETA factory        : 12/AUG/2012
3. Local fabrication
  - All spray tank will complete on 20/JULY/2012
  - ED Tank, Degreasing Tank & Zinc phosphate tank material preparation
  - 1st week AUG/2012, start fabricating in Aidil Colour bukit beruntung factory
3. Detail drawing revision update: 25~30/JULY/2012

WASTE WATER TREATMENT FABRICATION STATUS: FOR JUN 2012
WWT Fabrication status: JULY 2012 report
1. ACO FRP Tank / Tank raw material

2. Vessel & Air agitator 

3. ACO Tank / Fiber glass tank for mixing & Fully fiber glass tank