ED CONVEYOR FABRICATION STATUS: 15 JULY 2012

 1. Spray booth: Booth / Spray Pipe / Spray nozzle & accessories
 2. ED cirulation filtration & Accessories
 3. ED Spray booth / chiller / Cooling tower / ED room & structure
 4. Top spray booth / spray booth structure & circulation piping
 5. Oven partition for pre heat & conveyor tension adjusble unit
6. Rectifier / ED pump & order accessories
7. UF & Heat exchanger circulaion pump (Stainless steel)

15-JULY-2012 NEWS UPDATE
Refer to Taiwan fabrication status about 80% completion, we still continue to improve our progress, current we still waiting for the USA standard part's purchase and our target shipment dated on: 24/JULY/2012... for local fabrication with started in bukit beruntung ist week of AUG/2012

Status & Remark:
1. Taiwan  Shipment dated on 24/JULY/2012
2. Master schedule new revision: Rev 04 (Revise: More detail for installation and man power  
    arrangement)
   (Estimate schedule)
   - ETD Taiwan Port: 24/JULY/2012
   - ETA Port Klang  : 08/AUG/2012
   - ETA factory        : 12/AUG/2012
3. Local fabrication
  - All spray tank will complete on 20/JULY/2012
  - ED Tank, Degreasing Tank & Zinc phosphate tank material preparation
  - 1st week AUG/2012, start fabricating in Aidil Colour bukit beruntung factory
3. Detail drawing revision update: 25~30/JULY/2012

WASTE WATER TREATMENT FABRICATION STATUS: FOR JUN 2012
WWT Fabrication status: JULY 2012 report
1. ACO FRP Tank / Tank raw material

2. Vessel & Air agitator 

3. ACO Tank / Fiber glass tank for mixing & Fully fiber glass tank 

Monday, June 25, 2012

ELECTRO-COATING FOR AIDIL COLOUR SDN BHD
STATUS: 25/JUN/2012
   
STATUS: Bending work for spray booth

STATUS: Material for oven partition, spray booth
                 - Stainless steel     = 15ton
                 - Oven partition    = 29ton
                 - Structure            = 68 ton

 STATUS: Exhaust ducting

 STATUS: Oven partition frame

 STATUS: Oven partition

 STATUS: Spray booth, Mist spray booth & Spray booth foot

STATUS: ED sub tank, Flesh UF spray tank

Monday, June 11, 2012

ED System Status: 11/Jun/2012 - In progress of fabricating side spray booth

ED Oven Status: 11/Jun/2012 - In progress of fabricating Oven bottom partition

Sunday, June 10, 2012

Revision: 23, The layout has revise to R-23, due to adding LPG bulk tank and a location a area for future espension for other plating system upgrade, for detail please refer to below mention

1. Additional a LPG bulk tank at the conner of the factory area
2. Re location of Reverse Osmosis system to near oven area
3. Re location of waste water treatment to Reeverse Osmosis area
4. Modify the road to "R4320" as the dimesion, in order to let all trailer easy passing though and smooth exit during any emergency occur...

Wednesday, June 6, 2012

This is the ED Coating setup master schedule



Herewith the detail master schedule
a) Installation : Aug/2012
b) Commisioning: 15~30/Sep/2012


The ED coating system after setup will be almost silimar view as above picture